Sewer construction in Chatham will continue this upcoming week, weather permitting.
Starting on Monday, crews will begin gravity sewer installation work on Earl’s Way. Water main instillation on Tabitha Terrace and drainage installation on Oyster Pond Furlong will also take place during the week.
Meanwhile, next week crews will begin work on Jane’s way and also wrap up gravity sewer installation on Earl’s Way.
Normal work hours are from 7 a.m. to 5 p.m. Monday through Friday, and may extend to 7 p.m. in special circumstances.
Police details and signage will be in place to assist motorists in reaching their destination.